Use area × depth

For a rectangular area, multiply length by width. Convert the depth to metres, then multiply area by depth to get cubic metres.

Example

A 6 m × 4 m area is 24 m². At 5 cm depth, the depth is 0.05 m, so the volume is 1.2 m³. A 10% allowance would make the planning quantity about 1.32 m³.

Why actual quantities vary

Sand can settle, compact and contain moisture. Low spots can also increase the quantity required. Ask the supplier how their material is sold and whether the quoted quantity is based on loose or compacted volume.

Related tool

Use the Sand Calculator →

Convert the depth before calculating

The key step is to express depth in metres. For example, 25 mm is 0.025 m, 50 mm is 0.05 m and 100 mm is 0.10 m. Multiply the area in square metres by the depth in metres to get cubic metres. To convert cubic metres to litres, multiply by 1,000.

Worked example: a garden bed

A bed measuring 6 m by 4 m has an area of 24 m². If the specified sand layer is 50 mm deep, the volume is 24 × 0.05 = 1.2 m³, or about 1,200 litres. A 10% planning allowance gives 1.32 m³, or 1,320 litres. This is a geometric estimate; it does not predict compaction or account for uneven ground.

When the shape is not rectangular

For an L-shaped area, divide it into two non-overlapping rectangles, calculate each area, then add the results. For a circular area, use the appropriate circle-area formula before multiplying by depth. Avoid counting the same section twice when splitting a shape into smaller pieces.

Ordering and site checks

For related estimates, see the Sand Calculator, Soil Calculator and Paver Base Calculator.

Worked example: sand for a rectangular area

An area 4 m long and 3 m wide covered to a depth of 40 mm has a geometric volume of 4 × 3 × 0.04 = 0.48 m³, or 480 litres. The chosen depth should come from the intended application and system instructions. Convert millimetres to metres before multiplying, otherwise the volume will be wrong by a large factor.

Volume, weight and compaction are different

The calculation gives geometric volume. The delivered amount may differ if the sand settles or compacts, and converting cubic metres to tonnes requires a density appropriate to the actual product and moisture. Ask the supplier whether it sells loose volume, weight or bags and what conversion it uses.

Use the correct material for the job

Bedding sand, fill sand, play sand and other products are not automatically interchangeable. Keep sand separate from base aggregate and jointing material in the estimate. Use the Sand Calculator for a preliminary volume, then confirm product type and layer depth with the relevant project specification or supplier.